H.R. 523
110th Congress
Passed House
Douglas County, Washington, PUD Conveyance Act
To require the Secretary of the Interior to convey certain public land located wholly or partially within the boundaries of the Wells Hydroelectric Project of Public Utility District No. 1 of Douglas County, Washington, to the utility district.
Introduced
Jan 17, 2007
Committee
Oct 22, 2007
Passed House
Oct 22, 2007
Passed Senate
Next step
To President
Became law
+1 sections added
−0 removed
~2 modified
=2 unchanged
+127 words ·
−19 words
SEC. 2. Definitions Modified
SEC. 2. Definitions. In this Act:
(1) Public land. The term “public land” means the approximately 622 acres of Federal land managed by the Bureau of Land Management and identified for conveyance on the map prepared by the Bureau of Land Management entitled “Douglas County Public Utility District Proposal” and dated March 2, 2006.
(2) Secretary. The term “Secretary” means the Secretary of the Interior.
(3) PUD. The term “PUD” means the Public Utility District No. 1 of Douglas County, Washington.
(4) Wells hydroelectric project. The term “Wells Hydroelectric Project” means Federal Energy Regulatory Commission Project No. 2149.
SEC. 3. Conveyance of public land, Wells Hydroelectric Project, Public Utility District No. 1 of Douglas County, Washington Modified
⋯ Show 5 unchanged paragraphs
SEC. 3. Conveyance of public land, Wells Hydroelectric Project, Public Utility District No. 1 of Douglas County, Washington.
(a) Conveyance required. Notwithstanding the land use planning requirements of sections 202 and 203 of the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1712, 1713), and notwithstanding section 24 of the Federal Power Act (16 U.S.C. 818) and Federal Power Order for Project 2149, and subject to valid existing rights, if not later than 45 days after the date of completion of the appraisal required under subsection (b), the Public Utility District No. 1 of Douglas County, Washington, submits to the Secretary of the Interior an offer to acquire the public land for the appraised value, the Secretary shall convey, not later than 30 days after the date of the offer, to the PUD all right, title, and interest of the United States in and to the public land.
(b) Appraisal. Not later than 60 days after the date of enactment of this Act, the Secretary shall complete an appraisal of the public land. The appraisal shall be conducted in accordance with the “Uniform Appraisal Standards for Federal Land Acquisitions” and the “Uniform Standards of Professional Appraisal Practice”.
(c) Payment. Not later than 30 days after the date on which the public land is conveyed under this section, the PUD shall pay to the Secretary an amount equal to the appraised value of the public land as determined under subsection (b).
(d) Map and legal descriptions. As soon as practicable after the date of enactment of this Act, the Secretary shall finalize legal descriptions of the public land to be conveyed under this section. The Secretary may correct any minor errors in the map referred to in section 2 or in the legal descriptions. The map and legal descriptions shall be on file and available for public inspection in appropriate offices of the Bureau of Land Management.
(e) Costs of conveyance. As a condition of conveyance, any costs related to the conveyance under this section shall be paid by the PUD.
(f) Disposition of proceeds. The Secretary shall deposit the proceeds from the sale in the working capital fund Federal Land Disposal Account established by section 206 of the Federal Land Transaction Facilitation Act (43 U.S.C. 2305) to be expended to improve access to public lands administered by the Bureau of Land Management established by section 306 in the State of the Federal Land Policy and Management Act of 1976 (43 U.S.C. 1736). Washington.
SEC. 5. Retained authority Added
SEC. 5. Retained authority. The Secretary shall retain the authority to place conditions on the license to insure adequate protection and utilization of the public land granted to the Secretary in section 4(e) of the Federal Power Act (16 U.S.C. 797(e)) until the Federal Energy Regulatory Commission has issued a new license for the Wells Hydroelectric Project, to replace the original license expiring May 31, 2012, consistent with section 15 of the Federal Power Act (16 U.S.C. 808).