H.R. 4402 112th Congress Passed House
Congress.gov ↗

National Strategic and Critical Minerals Production Act of 2012

To require the Secretary of the Interior and the Secretary of Agriculture to more efficiently develop domestic sources of the minerals and mineral materials of strategic and critical importance to United States economic and national security and manufacturing competitiveness.

Introduced Apr 19, 2012
Committee Jul 9, 2012
Passed House Jul 12, 2012
To President  
Became law  
→
+0 sections added −0 removed ~1 modified =11 unchanged +285 words · −32 words
SEC. 102. Responsibilities of the lead agency Modified
SEC. 102. Responsibilities of the lead agency.
(a) In general. The lead agency with responsibility for issuing a mineral exploration or mine permit shall appoint a project lead who shall coordinate and consult with other agencies, cooperating agencies, project proponents and contractors to ensure that agencies minimize delays, set and adhere to timelines and schedules for completion of reviews, set clear permitting goals and track progress against those goals.
(b) The lead agency with responsibility for issuing a mineral exploration or mine permit may shall determine any such action would not constitute a major Federal action significantly affecting the quality of the human environment within the meaning of the National Environmental Policy Act of 1969 because if the procedural and substantive safeguards of the lead agency’s permitting process alone, any applicable State permitting process alone, or a combination of the two processes together provide an adequate mechanism to ensure that environmental factors are taken into account.
(c) The lead agency with responsibility for issuing a mineral exploration or mine permit shall enhance government coordination on permitting and review by avoiding duplicative reviews, minimizing paperwork and engaging other agencies and stakeholders early in the process. The lead agency shall consider the following best practices:
(1) Deferring to and relying upon baseline data, analysis and reviews preformed by State agencies with jurisdiction over the proposed project.
(2) Conducting reviews concurrently rather than sequentially to the extent practicable and when such concurrent review will expedite rather than delay a decision.
(d) At the request of a project proponent, the project lead of the agency with responsibility for issuing a mineral exploration or mine permit shall enter into an agreement with the project proponent and other cooperating agencies that sets time limits for each part of the permit review process including: including the following:
(1) The decision on whether to prepare an environmental impact statement. a document required under the National Environmental Policy Act of 1969.
(2) A determination of the scope of any environmental impact statement. document required under the National Environmental Policy Act of 1969.
(3) Preparation of any draft environmental impact statement.
(4) Preparation of a final environmental impact statement.
(3) The scope of and schedule for the baseline studies required to prepare a document required under the National Environmental Policy Act of 1969.
(4) Preparation of any draft document required under the National Environmental Policy Act of 1969.
(5) Preparation of a final document required under the National Environmental Policy Act of 1969.
(5) (6) Consultations required under applicable laws.
(6) (7) Submission and review of any comments required under applicable law.
(7) (8) Publication of any public notices required under applicable law.
(8) (9) A final or any interim decisions.
(e) In no case should the total review process described in section 2(d) subsection (d) exceed 30 months unless agreed to by the signatories of the agreement.
(f) The lead agency is not required to address agency or public comments that were not submitted during the public comment periods provided by the lead agency or otherwise required by law.
(g) The lead agency will determine the amount of financial assurance for reclamation of a mineral exploration or mining site, which must cover the estimated cost if the lead agency were to contract with a third party to reclaim the operations according to the reclamation plan, including construction and maintenance costs for any treatment facilities necessary to meet Federal, State or tribal environmental standards.
(h) This section shall apply with respect to a mineral exploration or mine permit for which an application was submitted before the date of the enactment of this Act if the applicant for the permit submits a written request to the lead agency for the permit. The lead agency shall begin implementing this section with respect to such application within 30 days after receiving such written request.
(i) With respect to strategic and critical materials within a federally administered unit of the National Forest System, the lead agency shall—
(1) exempt all areas of identified mineral resources in Land Use Designations, other than Non-Development Land Use Designations, in existence as of the date of the enactment of this Act from the procedures detailed at and all rules promulgated under part 294 of title 36, Code for Federal Regulations;
(2) apply such exemption to all additional routes and areas that the lead agency finds necessary to facilitate the construction, operation, maintenance, and restoration of the areas of identified mineral resources described in paragraph (1); and
(3) continue to apply such exemptions after approval of the Minerals Plan of Operations for the unit of the National Forest System.