SEC. 1.
Extension of time for Federal Energy Regulatory Commission project involving American Falls Reservoir.
Notwithstanding the time period specified in section 13 of the Federal Power Act (16 U.S.C. 806) that would otherwise apply to the Federal Energy Regulatory Commission project numbered 12423, the Federal Energy Regulatory Commission shall, at the request of the licensee for the project, and after reasonable notice and in accordance with the procedures of the Commission under that section, reinstate the license and extend the time period during which the licensee is required to commence the construction of project works to September 25, 2013.
¶
S. 334
112th Congress
Passed Senate
A bill to reinstate and extend the deadline for commencement of construction of a hydroelectric project involving the American Falls Reservoir.
Introduced
Feb 14, 2011
Committee
Aug 30, 2011
Passed Senate
Oct 18, 2011
Passed House
Next step
To President
Became law