SEC. 1.
Short title.
This Act may be cited as the “Expedited Delivery of Airport Infrastructure Act of 2020”.
¶
(1)
by striking “(1) if the cost necessarily” and inserting “(1)(A) if the cost necessarily”;
¶
(2)
by striking the semicolon at the end and inserting “; or”; and
¶
(3)
by adding at the end the following:
¶
(B)
if the cost is an incentive payment incurred in carrying out the project described in subparagraph (A) that is to be provided to a contractor upon early completion of a project, if—
¶
(i)
such payment does not exceed the lesser of 5 percent of the initial construction contract amount or $1,000,000;
¶
(ii)
the level of contractor’s control of, or access to, the worksite necessary to shorten the duration of the project does not negatively impact the operation of the airport;
¶
(iii)
the contract specifies application of the incentive structure in the event of unforeseeable, non-weather delays beyond the control of the contractor;
¶
(iv)
nothing in any agreement with the contractor prevents the airport operator from retaining responsibility for the safety, efficiency, and capacity of the airport during the execution of the grant agreement; and
¶
(v)
the Secretary determines that the use of an incentive payment is likely to increase airport capacity or efficiency or result in cost savings as a result of shortening the project’s duration;
¶
(b)
Technical correction.
Section 47110(e)(7) of title 49, United States Code, is amended by striking “(7) Partnership Program Airports.—” and inserting “(7) Partnership program airports.—”.
¶