S. 482 118th Congress Reported by committee
Congress.gov ↗

Klamath Power and Facilities Agreement Support Act

A bill to amend the Klamath Basin Water Supply Enhancement Act of 2000 to provide the Secretary of the Interior with certain authorities with respect to projects affecting the Klamath Basin watershed, and for other purposes.

Introduced Feb 16, 2023
Committee Nov 21, 2024
Passed House  
To President  
Became law  
→
+2 sections added −0 removed ~0 modified =2 unchanged +890 words · −0 words
SEC. 1. Short title Added
SEC. 1. Short title. This Act may be cited as the “Klamath Power and Facilities Agreement Support Act”.
SEC. 2. Klamath project water and power Added
SEC. 2. Klamath project water and power.
(a) Addressing water, power, and facilities management for irrigation. Section 4 of the Klamath Basin Water Supply Enhancement Act of 2000 (Public Law 106–498; 114 Stat. 2221; 132 Stat. 3886) is amended—
(1) in subsection (a)—
(A) by redesignating paragraphs (1), (2), and (3) as paragraphs (3), (4), and (6), respectively;
(B) by inserting before paragraph (3) (as so redesignated) the following:
(1) Agreement. The term Agreement means the agreement entitled “2016 Klamath Power and Facilities Agreement” and dated April 6, 2016.
(2) Covered contractor. The term covered contractor means—
(A) each Klamath Project Water User; and
(B) each landowner who is a Klamath Project contractor and receives water through transferred works of the Klamath Project that are operated by a Klamath Project Water User.
; and
(C) by inserting after paragraph (4) (as so redesignated) the following:
(5) Klamath Project Water User. The term Klamath Project Water User means a Klamath Project contractor who is a party to the Agreement.
; and
(2) by adding at the end the following:
(d) Restoration Activities.
(1) In general. The Secretary may—
(A) plan, design, construct, operate, and maintain projects in the Klamath Basin watershed, including—
(i) facilities to reduce fish entrainment;
(ii) projects that reduce or avoid impacts on aquatic resources of facilities involved in the storage or diversion of water for irrigation in the Klamath Project service area; and
(iii) projects that restore habitats in the Klamath Basin watershed, including Tribal fishery resources held in trust;
(B) undertake studies, including feasibility studies, and improvements that the Secretary determines to be necessary to implement this subsection;
(C) in implementing this subsection, enter into contracts, memoranda of understanding, financial assistance agreements, cost-sharing agreements, or other appropriate agreements with—
(i) State, Tribal, and local governmental agencies; and
(ii) private parties; and
(D) accept and expend non-Federal funds in order to facilitate implementation of this subsection.
(2) Costs. A covered contractor shall not bear any costs associated with any evaluation, design, construction, replacement, addition, or extraordinary maintenance activities carried out under paragraph (1).
(e) Pumping Plant D. The Secretary may enter into 1 or more agreements with the Tulelake Irrigation District to reimburse the Tulelake Irrigation District for not more than 69 percent of the cost incurred by the Tulelake Irrigation District for the operation and maintenance of Pumping Plant D, subject to the condition that the cost results in public benefits to the United States.
(f) Link River Dam and Keno Facility.
(1) Link River Dam.
(A) Operation. Subject to applicable law, the Secretary shall operate Link River Dam to provide water for—
(i) diversion for the Klamath Project; and
(ii) consistent with existing contracts between covered contractors and the Secretary, flood control.
(B) Responsibility for costs.
(i) In general. Notwithstanding any existing contracts and except as provided in clause (ii), covered contractors shall not be responsible for any cost associated with Link River Dam or any related land, facilities, dikes, or levees around Upper Klamath Lake, including costs of construction, extraordinary operation and maintenance, rehabilitation, betterment, and liabilities.
(ii) Routine operations and maintenance work.
(I) In general. Covered contractors shall be responsible for the appropriate share of routine operations and maintenance work associated with Link River Dam in accordance with the reclamation laws.
(II) Allocation to fish and wildlife benefits. The Secretary may allocate a proportionate share of the costs under subclause (I) to fish and wildlife benefits.
(2) Keno facility.
(A) In general. The Secretary shall operate the Keno Facility to maintain water levels upstream of Keno Dam to provide for diversion, canal maintenance, and flood control—
(i) consistent with—
(I) the contract between the Secretary and PacifiCorp numbered 14–06–200–3579A and executed January 4, 1968; and
(II) historic practice; and
(ii) subject to applicable law.
(B) Costs. A covered contractor shall not be responsible for any cost associated with the Keno Facility, including any responsibilities to landowners upstream of Keno Dam, including costs of construction, operations, maintenance, rehabilitation, betterment, liabilities, and any other costs.
(3) Subsequent transfer or assignment of responsibility. If the Secretary subsequently transfers or assigns responsibility for the operation of Link River Dam or the Keno Dam or Keno Facility to any other person or entity, the assignment or transfer shall include assignment of the obligations and conditions under paragraphs (1) and (2).
(b) Administration; effect.
(1) Compliance. In implementing the amendments made by this section, the Secretary of the Interior shall comply with—
(A) the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);
(B) the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.); and
(C) all other applicable laws.
(2) Effect. None of the amendments made by this section—
(A) modify any authority or obligation of the United States with respect to any Tribal trust or treaty obligation of the United States;
(B)
(i) create or determine any water right; or
(ii) affect any water right or water right claim in existence on the date of enactment of this Act; or
(C) authorize the use of Federal funds for the physical deconstruction of the Iron Gate, Copco 1, Copco 2, or John C. Boyle Dam located on the Klamath River in the States of California and Oregon.